August 03, 2017

Construction Update for Flowery School Trail and Verano Avenue Trail segments

On July 11, 2017, the construction contract was awarded to G.D. Nielson Construction, Inc. in the amount of $468,832. The contract includes paving 0.42 miles of trail and a new wooden pedestrian and bicycle bridge. Construction started on July 14 and is scheduled to be completed by October 4, 2017.