Larson Park Master Plan - Project Detail

Picnic area at Larson Park

Master Planning

After completing the Master Plan process in 2020 and the subsequent approval of the Master Plan by the Board of Supervisors in May of 2021, Regional Parks has begun developing the 100% construction plans and specifications for the approved renovations.

Implementation will be dependent on available funding of the project, which has a total budget of approximately 4.5 million dollars.

Anticipated Timeline

 Timeframe

Project Process

September 2024

Finalize 100% plans and specifications

October 2024

Advertise and bid Phase 1 site improvements

Fall 2024

Begin utility and site prep construction

November 2025

Complete Phase 1 construction

  

Community Workshops

Community Workshop #1

September 13, 2015 at La Luz Center – Sonoma, CA  (+/-30 members of the public attended)

Community Workshop #2

March 2, 2016 at Flowery Elementary School - Sonoma, CA  (+/-50 members of the public attended)

Community Workshop #3

August 23, 2017 at Flowery Elementary School – Sonoma, CA  (+/-30 members of the public attended)